Wärtsilä energy plant improve for largest gold mine in Senegal

The know-how group Wärtsilä will provide an 18 MW extension to the power producing facility and upgrade the electrical and automation system of the present power plant at the Sabodala-Massawa gold mine complex in Senegal, West Africa.
The mine is owned by Endeavour Mining, a quantity one world gold producer. The upgrading and extension project will permit for the whole integration of all the site’s energy generating capability, whereas guaranteeing the availability of the wanted electric energy to take care of and broaden the mine’s production schedules
he order with Wärtsilä was placed by Sabodala Gold Operations and it has been booked in Wärtsilä’s order intake in Q3 2022. The venture will be delivered underneath an entire engineering, procurement and construction (EPC) contract.
Sabodala-Massawa mine is the most important producing gold mine in Senegal and is positioned in the jap a part of the nation within the Kedougou area. ร้านซ่อมเครื่องวัดความดันโลหิต ’s deliberate mine enlargement will remodel Sabodala-Massawa right into a top-tier gold asset with incremental production.
“Wärtsilä has a depth of expertise in delivering power options for mining operations around the world. Not being related to the grid implies that the captive plant has to be capable of providing a dependable supply of electrical energy always, since no energy equals no manufacturing. The Wärtsilä 32 engines selected for this growth project have established a strong status for high effectivity and reliability under even essentially the most troublesome ambient conditions, eliminating revenue losses from power shortages,” said Marc Thiriet, Energy Business Director, Africa West, Wärtsilä.
The three Wärtsilä 32 engines to be installed are 20 per cent extra fuel efficient than the plant’s present engines. Their gasoline effectivity minimises the environmental impact by lowering harmful CO2 emissions. In addition to their excellent performance, they have the flexibleness to help a clean transition to the integration of solar power and vitality storage into the system. The upgrade of the electrical and automation system will optimise the interconnection and management for the present energy plant with the extension.
The project is expected to be completed and commissioned earlier than the tip of 2023.
Wärtsilä is Senegal’s leading supplier of power producing tools, and already has 543 MW of put in capability in altogether 20 energy crops within the nation. 458 MW of this capability is under Wärtsilä long-term service agreements.